Denver Legistar banner



File #: 19-0104    Version: 1
Type: Resolution Status: Adopted
File created: 2/4/2019 In control: Land Use, Transportation & Infrastructure Committee
On agenda: 3/11/2019 Final action: 3/11/2019
Title: A resolution approving a Contract between the City and County of Denver and Duran Excavating, Inc. to construct a new storm drain system including concrete flat work of the La Plata Peak General Storm project. Approves a contract with Duran Excavating, Inc. for $2,990,592.25 and for nine months to construct a new storm drain system that ties into existing storm drain infrastructure including concrete flatwork such as curb, gutter, sidewalk and asphalt paving as part of the La Plata Peak General Storm project located near 43rd Avenue and Sherman Street in Council District 9 and near Exposition Avenue and South Fillmore Street in Council District 6 (201846018). The last regularly scheduled Council meeting within the 30-day review period is on 4-1-19. The Committee approved filing this item at its meeting on 2-19-19.
Indexes: Zach Rothmier
Attachments: 1. RR19 0104 PW La Plata Peak.pdf, 2. 19-0104_Filed Resolution_Duran Excavating_201846018-00, 3. 19-0104_Contract_Duran Excavating_201846018-00, 4. 19-0104_Filed Resolution_Duran Excavating.pdf, 5. 19-0104 - signed
Contract Request Template (Contracts; IGAs; Leases)

Date Submitted: 2-5-19

Requesting Agency: Public Works
Division:

Subject Matter Expert Name:

Name: Jason Gallardo
Email: jason.gallardo@denvergov.org

Item Title & Description:
(Do not delete the following instructions)
These appear on the Council meeting agenda. Initially, the requesting agency will enter a 2-3 sentence description. Upon bill filling, the City Attorney's Office should enter the title above the description (the title should be in bold font).

Both the title and description must be entered between the red "title" and "body" below. Do not at any time delete the red "title" or "body" markers from this template.
title
A resolution approving a Contract between the City and County of Denver and Duran Excavating, Inc. to construct a new storm drain system including concrete flat work of the La Plata Peak General Storm project.
Approves a contract with Duran Excavating, Inc. for $2,990,592.25 and for nine months to construct a new storm drain system that ties into existing storm drain infrastructure including concrete flatwork such as curb, gutter, sidewalk and asphalt paving as part of the La Plata Peak General Storm project located near 43rd Avenue and Sherman Street in Council District 9 and near Exposition Avenue and South Fillmore Street in Council District 6 (201846018). The last regularly scheduled Council meeting within the 30-day review period is on 4-1-19. The Committee approved filing this item at its meeting on 2-19-19.
body

Affected Council District(s) or citywide? Council Districts 9 and 6

Contract Control Number: 201846018

Vendor/Contractor Name (including any "DBA"): Duran Excavating Inc.

Type and Scope of services to be performed:
The La Plata Peak General Storm contract has two separate project locations, one at 43rd Ave & Sherman St and the other at Exposition Ave & S Fillmore St. Each location will address lo...

Click here for full text