Denver Legistar banner



File #: 21-1049    Version: 1
Type: Resolution Status: Adopted
File created: 9/3/2021 In control: Business, Arts, Workforce, Climate & Aviation Services Committee
On agenda: 9/27/2021 Final action: 9/27/2021
Title: A resolution approving a proposed Contract between the City and County of Denver and AECOM Technical Services, Inc. concerning the 7th runway project at Denver International Airport. Approves a contract with AECOM Technical Services, Inc. for $22,516,537 and through 10-17-26, with a one-year option to extend, to provide project management services for the environmental review process for the 7th runway project at Denver International Airport (202057158-00). The last regularly scheduled Council meeting within the 30-day review period is on 10-18-21. The Committee approved filing this item at its meeting on 9-15-21.
Indexes: John Mahoney
Attachments: 1. RR21 1049 DIA AECOM, 2. 7th Runway Executive Summary, 3. BIZ Committee Presentation - 7th Runway Due Diligence Phase 9.15.2021 (FINAL), 4. 21-1049 Filed Resolution_AECOM Technical Services, 5. 21-1049 Contract_AECOM Technical Services, 6. 21-1049 Filed Resolution_AECOM Technical Services, 7. 21-1049 - signed

Contract Request Template (Contracts; IGAs; Leases)

 

Date Submitted: 9-3-21

 

Requesting Agency: Denver International Airport

                               Division:

 

Subject Matter Expert Name:

Name:        Carolina Flores                                                              

Email:        Carolina.Flores@flydenver.com                                                               

 

Item Title & Description:

(Do not delete the following instructions)

These appear on the Council meeting agenda. Initially, the requesting agency will enter a 2-3 sentence description. Upon bill filling, the City Attorney’s Office should enter the title above the description (the title should be in bold font).

 

Both the title and description must be entered between the red “title” and “body” below.  Do not at any time delete the red “title” or “body” markers from this template.

title

A resolution approving a proposed Contract between the City and County of Denver and AECOM Technical Services, Inc. concerning the 7th runway project at Denver International Airport.

Approves a contract with AECOM Technical Services, Inc. for $22,516,537 and through 10-17-26, with a one-year option to extend, to provide project management services for the environmental review process for the 7th runway project at Denver International Airport (202057158-00). The last regularly scheduled Council meeting within the 30-day review period is on 10-18-21. The Committee approved filing this item at its meeting on 9-15-21.                                                          

body

 

Affected Council District(s) or citywide? Council District 11

 

Contract Control Number: 202057158-00

 

Vendor/Contractor Name (including any “DBA”): AECOM Technical Services, Inc.

 

Type and Scope of services to be performed:

The PMT will lead, direct, coordinate, and manage the scope of work of the Design and Environmental Services Consultant for each Milestone that is defined in coordination with DEN, and the Federal Aviation Administration (FAA) as required in the scope of services outlined in the Request for Qualification (RFQ).  The final negotiated contract amount approved by DEN will be for Milestone 2 (Pre-Environmental Review) and Milestone 3 (Environmental Review) only and will be considered the not-to-exceed value of the contract.  The not-to-exceed amount is not guaranteed to the Design Consultant and all work will be performed, pursuant to Task Orders, on a time and material basis through these Milestones, based upon budget and Executive Leadership approval.  Future funding and approval to proceed with Milestone 4 will be determined in the future, which will require DEN Administration, Mayor, and City Council approval. 

 

The FAA has verbally notified DEN that the Program Management Services contract will not receive AIP grant reimbursables during the Environmental Review phase.  Further AIP grant match will be considered for the final design and construction of the 7th Runway, which is Milestone 4.

Location (if applicable):

 

WBE/MBE/DBE goals that were applied, if applicable (construction, design, Airport concession contracts):

25%

Are WBE/MBE/DBE goals met (if applicable)?

 

Is the contract new/a renewal/extension or amendment?

 

Was this contractor selected by competitive process or sole source?

Competitive process                     

For New contracts

Term of initial contract: 10/18/2021 - 10/17/2026

 

Options for Renewal:

                     How many renewals (i.e. up to 2 renewals)? 1

                     Term of any renewals (i.e. 1 year each): 1 year

 

Cost of initial contract term: $22,516,537.00

 

Cost of any renewals:

 

Total contract value council is approving if all renewals exercised:

 

For Amendments/Renewals Extensions:

Is this a change to cost/pricing; length of term; terms unrelated to time or price (List all that apply)?

 

If length changing

What was the length of the term of the original contract?

 

What is the length of the extension/renewal?

 

What is the revised total term of the contract?

 

If cost changing

What was the original value of the entire contract prior to this proposed change?

 

What is the value of the proposed change?

 

What is the new/revised total value including change?

 

If terms changing

Describe the change and the reason for it (i.e. compliance with state law, different way of doing business etc.)