Transportation and
Infrastructure
Minutes
Wednesday, April 8, 2026, 1:30 PM
Chair: Shontel Lewis, Vice Chair: Chris Hinds
Members: Flor Alvidrez, Kevin Flynn, Stacie Gilmore, Paul Kashmann, Amanda Sandoval
Staff: Melissa Mata
Consent Items
Approves a contract with CUTLER REPAVING, INC. for $6,533,912.21
with a term of NTP + 180 Days for roto-milling asphalt pavement and
paving the top lift using a hot-in-place recycling treatment for 95 lane miles
of local, collector, and arterial streets, citywide (DOTI-202682911).
Council Resolution 26-0466 was approved by consent.
Approves a contract with Ash & White Construction Company dba WCG
Construction for $10,000,000.00 and for five years for on call landside
facilities maintenance and repair services at Denver International Airport
(DEN) in Council District 11 (PLANE-202683427).
Council Resolution 26-0468 was approved by consent.
Amends a contract with Ricondo & Associates, Inc by adding $750,000 for
a new total of $2,250,000 and two years for a new end date of 9-29-2028
to provide continued, urgent, on-call airport planning services at Denver
International Airport, in Council District 11
(PLANE-202266043/PLANE-202683157-01).
Council Resolution 26-0469 was approved by consent.
Approves a contract with Sky Blue Builders, LLC for $10,000,000.00 and
for five years for on call landside facilities maintenance and repair services
at Denver International Airport (DEN) in Council District 11
(PLANE-202579248).
Council Resolution 26-0470 was approved by consent.
Approves a contract with A-1 Chipseal Company for $6,133,405.00 with a
term of NTP + 120 Days for cape seal and crack seal work will be
performed in various locations throughout the City and County of Denver.
Approximately 125 lane miles, primarily consisting of local streets, will be
treated with cape seal resurfacing (chip + slurry) for the 2026 Citywide
Chip Seal and Crack Seal, citywide (DOTI-202682986).