Contract Request Template (Contracts; IGAs; Leases)
Date Submitted: 3-22-21
Requesting Agency: Denver International Airport
Division:
Subject Matter Expert Name:
Name: Angela Casias |
Email: Angela.Casias@flydenver.com |
Item Title & Description:
(Do not delete the following instructions)
These appear on the Council meeting agenda. Initially, the requesting agency will enter a 2-3 sentence description. Upon bill filling, the City Attorney’s Office should enter the title above the description (the title should be in bold font).
Both the title and description must be entered between the red “title” and “body” below. Do not at any time delete the red “title” or “body” markers from this template.
title
A resolution approving a proposed Contract between the City and County of Denver and IHC Scott, Inc. concerning the rehabilitation of the Runway 16L-34R and Taxiway Z complex at Denver International Airport.
Approves a contract with IHC Scott, Inc. for $23,555,608.22 and for 140 days for the rehabilitation of the Runway 16L-34R and Taxiway Z complex, which will remove and replace deteriorated concrete pavement and upgrade the airfield lighting system at Denver International Airport (202056997). The last regularly scheduled Council meeting within the 30-day review period is on 5-3-21. The Committee approved filing this item at its meeting on 3-31-21.
body
Affected Council District(s) or citywide? Council District 11
Contract Control Number: 202056997
Vendor/Contractor Name (including any “DBA”): IHC Scott, Inc.
Type and Scope of services to be performed:
This project will remove and replace deteriorated concrete pavement, joint sealant, and improve deficient taxiway safety areas on the Runway 16L-34R and Taxiway Z complex. The airfield lighting system will be upgraded with new LED fixtures, transformer, cables, and guidance signs. In addition, the project will refresh the surface painted pavement markings, and address surface drainage and slope issues.
Location (if applicable):
WBE/MBE/DBE goals that were applied, if applicable (construction, design, Airport concession contracts):
16.08%
Are WBE/MBE/DBE goals met (if applicable)?
Is the contract new/a renewal/extension or amendment?
Was this contractor selected by competitive process or sole source?
Competitive process
For New contracts
Term of initial contract: 140 calendar days from NTP
Options for Renewal:
How many renewals (i.e. up to 2 renewals)?
Term of any renewals (i.e. 1 year each):
Cost of initial contract term: $23,555,608.22
Cost of any renewals:
Total contract value council is approving if all renewals exercised:
For Amendments/Renewals Extensions:
Is this a change to cost/pricing; length of term; terms unrelated to time or price (List all that apply)?
If length changing
What was the length of the term of the original contract?
What is the length of the extension/renewal?
What is the revised total term of the contract?
If cost changing
What was the original value of the entire contract prior to this proposed change?
What is the value of the proposed change?
What is the new/revised total value including change?
If terms changing
Describe the change and the reason for it (i.e. compliance with state law, different way of doing business etc.)