File #: 23-0847    Version: 1
Type: Resolution Status: Adopted
File created: 6/18/2023 In control: Land Use, Transportation & Infrastructure Committee
On agenda: 7/10/2023 Final action: 7/10/2023
Title: A resolution approving a proposed Contract between the City and County of Denver and Brannan Construction Company to support the implementation of wastewater infrastructure improvement projects and programs, citywide. Approves a contract with Brannan Construction Company for $2,000,000 and two years to support the implementation of wastewater infrastructure improvement projects and programs, citywide (202366472). The last regularly scheduled Council meeting within the 30-day review period is on 7-31-2023. The Committee approved filing this item at its meeting on 6-27-2023.
Indexes: Lucas Palmisano
Attachments: 1. RR23-0847_DOTI_202366472 Ordinance Request, 2. 23-0847 Filed Resolution_Brannan Construction Company 202366472-00, 3. 23-0847 Contract_Brannan Construction Company 202366472-00, 4. 23-0847 Filed Resolution_Brannan Construction Company, 5. 23-0847_signed

Contract Request Template (Contracts; IGAs; Leases)

 

Date Submitted: 6-26-2023

 

Requesting Agency: Department of Transportation and Infrastructure

                               Division:

 

Subject Matter Expert Name:  Aaron McMichael, Michele Foust
Email Address:
aaron.mcmichael@denvergov.org <mailto:aaron.mcmichael@denvergov.org>

      Michele.foust@denvergov.org <mailto:Michele.foust@denvergov.org>

Phone Number:

 

Item Title & Description:

(Do not delete the following instructions)

These appear on the Council meeting agenda. Initially, the requesting agency will enter a 2-3 sentence description. Upon bill filling, the City Attorney’s Office should enter the title above the description (the title should be in bold font).

 

Both the title and description must be entered between the red “title” and “body” below.  Do not at any time delete the red “title” or “body” markers from this template.

title

A resolution approving a proposed Contract between the City and County of Denver and Brannan Construction Company to support the implementation of wastewater infrastructure improvement projects and programs, citywide.

Approves a contract with Brannan Construction Company for $2,000,000 and two years to support the implementation of wastewater infrastructure improvement projects and programs, citywide (202366472). The last regularly scheduled Council meeting within the 30-day review period is on 7-31-2023. The Committee approved filing this item at its meeting on 6-27-2023.

body

 

Affected Council District(s) or citywide?

Citywide

 

Contract Control Number:

202366472

 

Vendor/Contractor Name (including any “DBA”):

Brannan Construction Company

 

Type and Scope of services to be performed:

A 2-year long contract designed to support the implementation of the Wastewater Infrastructure Improvement Projects and/or Programs. Work performed will include but is not limited to: replacement of sanitary and storm sewer infrastructure; Infrastructure Program systems support and/or development; cured-in-place lining for water, storm, and sanitary infrastructure; work in open channel waterways; environmental site investigation and/or early construction activities; negotiating early site access and agreements; structural rehabilitation of manholes, inlets, and other wastewater infrastructure, installation or stabilization of concrete flatwork, street infrastructure, or subgrades; promoting storm drainage in the City Right-of-way, City parks, or other City owned facilities and land; utility relocation and coordination; compliance with regulations including the American Disability Act; other work to satisfy City obligations under State, Federal, and Army Corp issued permits or other City agreements associated with Infrastructure Projects involving new construction, water quality, and drainage way improvements. This contract will be composed of multiple events and used on an as-needed basis. Contract term is two years and the maximum contract amount is $2,000,000.00 (contract amount is no guarantee of work).

 

Location (if applicable):

 

WBE/MBE/DBE goals that were applied, if applicable (construction, design, Airport concession contracts):

M/WBE

 

Are WBE/MBE/DBE goals met (if applicable)?

7%

TBD; MWBE Equity, Diversity and Inclusion Plan was approved by DSBO.

 

Is the contract new/a renewal/extension or amendment?

New

 

Was this contractor selected by competitive process or sole source?

Competitive process

 

For New contracts

Term of initial contract:

NTP + 2years

 

Options for Renewal:

                     How many renewals (i.e. up to 2 renewals)?

                     Term of any renewals (i.e. 1 year each):

 

Cost of initial contract term:

$2,000,000

 

Cost of any renewals:

 

Total contract value council is approving if all renewals exercised:

 

For Amendments/Renewals Extensions:

Is this a change to cost/pricing; length of term; terms unrelated to time or price (List all that apply)?

 

If length changing

What was the length of the term of the original contract?

 

What is the length of the extension/renewal?

 

What is the revised total term of the contract?

 

If cost changing

What was the original value of the entire contract prior to this proposed change?

 

What is the value of the proposed change?

 

What is the new/revised total value including change?

 

If terms changing

Describe the change and the reason for it (i.e. compliance with state law, different way of doing business etc.)