Title: A resolution approving a proposed Contract between the City and County of Denver and Merrick & Company for professional engineering and design services. Approves a contract with Merrick & Company for $25 million and for five years for all horizontal infrastructure design work and other professional services to support the successful delivery of the National Western Center Capital Build program including construction drawings and specifications of site wide infrastructure, permitting support and necessary stakeholder coordination in Council District 9 (201840729). The last regularly scheduled Council meeting within the 30-day review period is on 4-23-18. The Committee approved filing this resolution at its meeting on 3-20-18.
Indexes: Zach Rothmier
Attachments: 1. RR18 0297 PW NWC Merrick Terms, 2. RR18 0297 PW NWC Merrick, 3. 18-0297_Contract_Merrick and Company.201840729-00, 4. 18-0297_Filed Resolution_Merrick and Company.201840729-00, 5. 18-0297 Filed Resolution_Merrick and Company.201840729-00.pdf, 6. 18-0297 - signed

Contract Request Template (Contracts; IGAs; Leases)

 

Date Submitted: 3-13-18

 

Requesting Agency: Public Works

                               Division:

 

Name: Angela Casias

▪ Phone: 720-913-8529

Email: angela.casias@denvergov.org

 

Item Title & Description:

(Do not delete the following instructions)

These appear on the Council meeting agenda. Initially, the requesting agency will enter a 2-3 sentence description. Upon bill filling, the City Attorney’s Office should enter the title above the description (the title should be in bold font).

 

Both the title and description must be entered between the red “title” and “body” below.  Do not at any time delete the red “title” or “body” markers from this template.

title

A resolution approving a proposed Contract between the City and County of Denver and Merrick & Company for professional engineering and design services.

Approves a contract with Merrick & Company for $25 million and for five years for all horizontal infrastructure design work and other professional services to support the successful delivery of the National Western Center Capital Build program including construction drawings and specifications of site wide infrastructure, permitting support and necessary stakeholder coordination in Council District 9 (201840729). The last regularly scheduled Council meeting within the 30-day review period is on 4-23-18. The Committee approved filing this resolution at its meeting on 3-20-18.

body

 

Affected Council District(s) or citywide? CD 9

 

Contract Control Number: 201840729

 

Vendor/Contractor Name (including any “DBA”): Merrick & Company

 

Type and Scope of services to be performed:

 The selected Horizontal Portfolio Designer, Merrick and Company, will serve as the single point control for campus wide, integrated enabling works and infrastructure design to support the successful delivery of the National Western Center Capital Build Program on a Task Order by Task Order basis. The Horizontal Designer will provide construction drawings and specifications to the Horizontal Integrated Construction Services Contractor for construction of site wide infrastructure, including mass earthwork, environmental cleanup, utilities, all right-of-way construction, riverfront open space, bridge structures and ‘pad ready’ sites for NWC venue construction and plazas, including the Colorado State University and Western Stock Show Association venues. The scope of services also includes all permitting support and regulatory requirements as related to the scope of work, necessary stakeholder coordination, development of probable costs for all improvements, preparation of sequencing plans to accommodate the operational switchover required by the overall National Western Center campus Capital Build, and construction support services to the Horizontal Integrated Construction Services Contractor.

 

Location (if applicable):

 

WBE/MBE/DBE goals that were applied, if applicable (construction, design, Airport concession contracts):

 

Are WBE/MBE/DBE goals met (if applicable)? W/MBE     19%

 

Is the contract new/a renewal/extension or amendment?

 

Was this contractor selected by competitive process or sole source?

                     

For New contracts

Term of initial contract: Five years

 

Options for Renewal:

                     How many renewals (i.e. up to 2 renewals)?

                     Term of any renewals (i.e. 1 year each):

 

Cost of initial contract term: $25,000,000

 

Cost of any renewals:

 

Total contract value council is approving if all renewals exercised:

 

For Amendments/Renewals Extensions:

Is this a change to cost/pricing; length of term; terms unrelated to time or price (List all that apply)?

 

If length changing

What was the length of the term of the original contract?

 

What is the length of the extension/renewal?

 

What is the revised total term of the contract?

 

If cost changing

What was the original value of the entire contract prior to this proposed change?

 

What is the value of the proposed change?

 

What is the new/revised total value including change?

 

If terms changing

Describe the change and the reason for it (i.e. compliance with state law, different way of doing business etc.)