Denver Legistar banner



File #: 22-0909    Version: 1
Type: Resolution Status: Adopted
File created: 7/25/2022 In control: Land Use, Transportation & Infrastructure Committee
On agenda: 8/22/2022 Final action: 8/22/2022
Title: A resolution approving a proposed Contract between the City and County of Denver and Hamon Infrastructure, Inc., to complete the South Broadway Multimodal Improvement Project as part of the Elevate Denver Bond program. Approves a contract with Hamon Infrastructure, Inc. for $14,260,000 and one-year to complete the South Broadway Multimodal Improvement Project as part of the Elevate Denver Bond program, located in Council District 7 (202262166). The last regularly scheduled Council meeting within the 30-day review period is on 9-12-2022. The Committee approved filing this item at its meeting on 8-2-2022.
Indexes: Lucas Palmisano
Attachments: 1. RR22-0909 202262166 Ordinance Request, 2. 22-0909 Filed Resolution_Hamon Infrastructure, Inc. - 202262166-00, 3. 22-0909 Agr_Hamon Infrastructure, Inc_202262166-00, 4. 22-0909 Filed Resolution_Hamon Infrastructure, Inc. - 202262166-00, 5. 22-0909 - signed

Contract Request Template (Contracts; IGAs; Leases)

 

Date Submitted: 8-1-2022

 

Requesting Agency: Department of Transportation and Infrastructure

                               Division:

 

Subject Matter Expert Name: James Colbert                                                             
Email Address
:      james.colbert@denvergov.org                                                             
Phone Number:

 

Item Title & Description:

(Do not delete the following instructions)

These appear on the Council meeting agenda. Initially, the requesting agency will enter a 2-3 sentence description. Upon bill filling, the City Attorney’s Office should enter the title above the description (the title should be in bold font).

 

Both the title and description must be entered between the red “title” and “body” below.  Do not at any time delete the red “title” or “body” markers from this template.

title

A resolution approving a proposed Contract between the City and County of Denver and Hamon Infrastructure, Inc., to complete the South Broadway Multimodal Improvement Project as part of the Elevate Denver Bond program.

Approves a contract with Hamon Infrastructure, Inc. for $14,260,000 and one-year to complete the South Broadway Multimodal Improvement Project as part of the Elevate Denver Bond program, located in Council District 7 (202262166). The last regularly scheduled Council meeting within the 30-day review period is on 9-12-2022. The Committee approved filing this item at its meeting on 8-2-2022.

body

 

Affected Council District(s) or citywide? 7

 

Contract Control Number: 202262166

 

Vendor/Contractor Name (including any “DBA”): Hamon Infrastructure, Inc.

 

Type and Scope of services to be performed: The South Broadway Multimodal project will construct two-way protected bike lanes from Center Ave. to 7th Ave/Speer Blvd. The project work elements also include signal improvements, ADA improvements, concrete and asphalt paving, signing and striping, drainage and landscaping improvements

 

Location (if applicable): Center Avenue to 7th Avenue/Speer Boulevard

 

WBE/MBE/DBE goals that were applied, if applicable (construction, design, Airport concession contracts): DBE

 

Are WBE/MBE/DBE goals met (if applicable)? 13%- ? Loya Construction, Inc. (10.83%); American Sign Company (2.17%)

 

 

Is the contract new/a renewal/extension or amendment? New

 

Was this contractor selected by competitive process or sole source?

                     Competitive

For New contracts

Term of initial contract: NTP+ 365 days

 

Options for Renewal:

                     How many renewals (i.e. up to 2 renewals)?

                     Term of any renewals (i.e. 1 year each):

 

Cost of initial contract term: $14,260,000.00

 

Cost of any renewals:

 

Total contract value council is approving if all renewals exercised:

 

For Amendments/Renewals Extensions:

Is this a change to cost/pricing; length of term; terms unrelated to time or price (List all that apply)?

 

If length changing

What was the length of the term of the original contract?

 

What is the length of the extension/renewal?

 

What is the revised total term of the contract?

 

If cost changing

What was the original value of the entire contract prior to this proposed change?

 

What is the value of the proposed change?

 

What is the new/revised total value including change?

 

If terms changing

Describe the change and the reason for it (i.e. compliance with state law, different way of doing business etc.)