File #: 23-1810    Version: 1
Type: Resolution Status: Approval Review
File created: 11/13/2023 In control: Land Use, Transportation & Infrastructure Committee
On agenda: 11/21/2023 Final action:
Title: Approves a contract with Stream Design, LLC for $1,032,525.28 and 791 days for architectural and engineering design services for the design of the 47th and Walden Park, in Council District 11. 202371123.
Indexes: Lucas Palmisano
Attachments: 1. RR23-1810_DOTI_202371123 - 47th Walden Park Resolution Request_Stream Design

Contract Request Template (Contracts; IGAs; Leases)

 

Date Submitted: 11-20-2023

 

Requesting Agency: DOTI

                               Division:

 

Subject Matter Expert Name: Jason Gallardo
Email Address:
Jason.gallardo@denvergov.org <mailto:Jason.gallardo@denvergov.org>
Phone Number:

 

Item Title & Description:

(Do not delete the following instructions)

These appear on the Council meeting agenda. Initially, the requesting agency will enter a 2-3 sentence description. Upon bill filling, the City Attorney’s Office should enter the title above the description (the title should be in bold font).

 

Both the title and description must be entered between the red “title” and “body” below.  Do not at any time delete the red “title” or “body” markers from this template.

title

Approves a contract with Stream Design, LLC for $1,032,525.28 and 791 days for architectural and engineering design services for the design of the 47th and Walden Park, in Council District 11. 202371123.

body

 

Affected Council District(s) or citywide?

Council District 11

Contract Control Number:

202371123

Vendor/Contractor Name (including any “DBA”):

Stream Design, LLC

Type and Scope of services to be performed:

Denver Parks and Recreation (“DPR”) and the Department of Transportation and Infrastructure (“DOTI”) has solicited Requests for Qualifications from teams to provide Landscape, Architectural, and Engineering Professional services for 47th and Walden Park. The scope of design services includes development of the concept plans through schematic design and design development, preparation of construction documents, coordination with the selected General Contractor or Construction Manager/General Contractor (CM/GC), and construction administration through project completion.

Location (if applicable):

 

WBE/MBE/DBE goals that were applied, if applicable (construction, design, Airport concession contracts):

WBE/MBE

Are WBE/MBE/DBE goals met (if applicable)?

24%

Is the contract new/a renewal/extension or amendment?

new

Was this contractor selected by competitive process or sole source?

Competitive process                     

For New contracts

 

 Current Contract Amount (A)

Additional Funds (B)

Total Contract Amount (A+B)

$1,032,525.28

Enter if applicable

$1,032,525.28

 

Current Contract Term

Added Time

New Ending Date

NTP + 791 days

Enter if applicable

NTP + 791 days