Denver Legistar banner



File #: 22-0357    Version: 1
Type: Resolution Status: Adopted
File created: 3/21/2022 In control: Land Use, Transportation & Infrastructure Committee
On agenda: 5/2/2022 Final action: 5/2/2022
Title: A resolution approving a proposed Contract between the City and County of Denver and Silva Construction, Inc. for the 2022 Citywide ADA Ramp and Concrete Repair Phase 2 Project. Approves a contract with Silva Construction, Inc. for $2,535,000 and for 200 days for the 2022 Citywide ADA Ramp and Concrete Repair Phase 2 Project (202161645). The last regularly scheduled Council meeting within the 30-day review period is on 5-23-22. The Committee approved filing this item at its meeting on 3-29-22.
Indexes: Zach Rothmier
Attachments: 1. RR22 0357 DOTI SIlva 202161645 Ordinance Request, 2. 22-0357 Contract_SIlva Construction, Inc., 3. 22-0357 Filed Resolution_Silva Construction, Inc. 202161645, 4. 22-0357 Filed Resolution_Silva Construction, Inc., 5. 22-0357 - signed
Contract Request Template (Contracts; IGAs; Leases)

Date Submitted: 3/21/22

Requesting Agency: DOTI
Division:

Subject Matter Expert Name: Jason Gallardo
Email Address: Jason.gallardo@denvergov.org
Phone Number:

Item Title & Description:
(Do not delete the following instructions)
These appear on the Council meeting agenda. Initially, the requesting agency will enter a 2-3 sentence description. Upon bill filling, the City Attorney's Office should enter the title above the description (the title should be in bold font).

Both the title and description must be entered between the red "title" and "body" below. Do not at any time delete the red "title" or "body" markers from this template.
title
A resolution approving a proposed Contract between the City and County of Denver and Silva Construction, Inc. for the 2022 Citywide ADA Ramp and Concrete Repair Phase 2 Project.
Approves a contract with Silva Construction, Inc. for $2,535,000 and for 200 days for the 2022 Citywide ADA Ramp and Concrete Repair Phase 2 Project (202161645). The last regularly scheduled Council meeting within the 30-day review period is on 5-23-22. The Committee approved filing this item at its meeting on 3-29-22.
body

Affected Council District(s) or citywide? Citywide

Contract Control Number: 202161645

Vendor/Contractor Name (including any "DBA"): Silva Construction, Inc.

Type and Scope of services to be performed:
Removal and replacement of deficient concrete curbs, gutters, sidewalk panels, valley gutters, concrete streets, and alley pavement. Also includes asphalt pavement and landscaping/irrigation restoration.

Location (if applicable): Various citywide

WBE/MBE/DBE goals that were applied, if applicable (construction, design, Airport concession contracts): 30%

Are WBE/MBE/DBE goals met (if applicable)? Yes - Prime Contractor is SBE certified and will self-perform all work.


Is the contract new/a renewal/extension or amendment? New

Was this contractor selected by ...