Title:
|
Approves the fourth amendment to the contract with Wenk Associates for Parkfield Lake Park to increase the amount for additional professional services by $7,250 for a maximum contract amount of $715,502 to include surveying, structural engineering and onsite storm water inspection. This contract ammendment will provide additional design services to be paid out of the original 2008 Bond project budget for
design of storm drain improvements for an existing drain system that was impacted by the current construction.
Also included are fees for additional Construction Observation services as required by an increased construction period based on changes to the scope of construction. Contract performance period will not change.
|