Title:
|
Amends the on-call contract with Parsons Commercial Technology Group to increase the contract capacity from $42,000,000 to $48,000,000 and establishes June 1, 2015, as the cutoff for any additional change orders for wastewater work, including Hampden Heights Outfall and Cherry Creek North Outfall Project (part of University and Josephine reconstruction) in Council Districts 4, 6 and 10. (LAND USE, TRANSPORTATION & INFRASTRUCTURE) Amends the contract with Parsons Commercial Technology Group to increase the maximum from $42 million to $48 million and establish a contract term end date of June 1, 2015, for the University and Josephine Reconstruction and Cherry Creek North Outfall Project in Council District 10. The last reguarly scheduled Council meeting within the 30-day review period is on 2-20-14. The Committee approved filing this bill by consent on 1-16-14.
|