Title:
|
Amends a contract with Westover Corporation to extend the term through 10-01-14 and to add $292,579 for a total contract amount of $690,580.05 for upgrades to the Denver Art Museum’s camera and network infrastructure system (201311717). (LAND USE, TRANSPORTATION & INFRASTRUCTURE ) Amends a contract with Westover Corporation to extend the term through 10-01-14 and add $292,579 for a total contract amount of $690,580.05 for upgrades to the Denver Art Museum’s camera and network infrastructure system (201311717). The last regularly scheduled Council meeting within the 30-day review period is on . The Committee approved filing this bill by consent on 5-1-14.
|