Title:
|
Amends the contract with CH2M Hill to add $3,713,516, for a new total of $6,201,186, and extend the term by 4 years, through 2016, for the Peoria Grade Separation project - Phase III, advanced engineering, procurement and support services during design and construction (201102842). (LAND USE, TRANSPORTATION & INFRASTRUCTURE) Amends the contract with CH2M Hill to add $3,713,516, for a new total of $6,201,186, and extend the term by 4 years, through 2016, for the Peoria Grade Separation project -Phase III, advanced engineering, procurement and support services during design and construction (201102842). The last regularly scheduled Council meeting within the 30-day review period is on 8-6-12. The Committee approved filing this bill by consent on 7-5-12.
|