File #: 17-0385    Version: 1
Type: Bill Status: Failed
File created: 3/28/2017 In control: Land Use, Transportation & Infrastructure Committee
On agenda: 6/5/2017 Final action: 6/5/2017
Title: A bill for an ordinance approving a proposed Amendment to Agreement between the City and County of Denver and Urban Drainage and Flood Control District regarding flood control improvements for Sanderson Gulch Lipan Street to South Platte River. Amends an intergovernmental agreement with Urban Drainage and Flood Control District by adding $1 million for a new total of $2.6 million to partially fund flood control improvements along Sanderson Gulch from Lipan Street to the South Platte River to reduce risk of flooding from 10, 25, 50 and 100-year storm events in Council District 7 (201523631). The last regularly scheduled Council meeting within the 30-day review period is on 6-26-17. The Committee approved filing this bill by consent on 4-4-17.
Indexes: Zach Rothmier
Attachments: 1. RR17 0385 PW UDFCD Sanderson Gulch Agreement, 2. RR17 0385 PW UDFCD Sanderson Gulch Request, 3. RR17 0385 PW UDFCD Sanderson Gulch Terms, 4. 17-0385 Filed Bill_Urban Drainage & Flood Control District 201523631-02, 5. 17-0385 Amendment to Agreement_Urban Drainage and Flood Control District 201523631-02, 6. 17-0385 Filed Bill_Urban Drainage & Flood Control District 201523631-02.pdf

Contract Request Template (Contracts; IGAs; Leases)

 

Date Submitted: 03-28-17

 

Requesting Agency: Public Works

                               Division:

 

§                     Name:                     Angela Casias

§                     Phone:                     720-913-8529

§                     Email:                     Angela.casias@denvergov.org

 

Item Title & Description:

(Do not delete the following instructions)

These appear on the Council meeting agenda. Initially, the requesting agency will enter a 2-3 sentence description. Upon bill filling, the City Attorney’s Office should enter the title above the description (the title should be in bold font).

 

Both the title and description must be entered between the red “title” and “body” below.  Do not at any time delete the red “title” or “body” markers from this template.

title

A bill for an ordinance approving a proposed Amendment to Agreement between the City and County of Denver and Urban Drainage and Flood Control District regarding flood control improvements for Sanderson Gulch Lipan Street to South Platte River.

Amends an intergovernmental agreement with Urban Drainage and Flood Control District by adding $1 million for a new total of $2.6 million to partially fund flood control improvements along Sanderson Gulch from Lipan Street to the South Platte River to reduce risk of flooding from 10, 25, 50 and 100-year storm events in Council District 7 (201523631). The last regularly scheduled Council meeting within the 30-day review period is on 6-26-17. The Committee approved filing this bill by consent on 4-4-17.

body

 

Affected Council District(s) or citywide? Council District 7

 

Contract Control Number: 201523631

 

Vendor/Contractor Name (including any “DBA”): Urban Drainage and Flood Control District

 

Type and Scope of services to be performed: Original contract (201523631) and first amendment total is $1,600,000; this amendment will add $1,000,000 in funding to the Sanderson Gulch project.  These funds will be held by Urban Drainage and used for design until design is complete.  Any remaining funds will be remitted to the City for construction costs.  The City will provide matching funds of $7,400,000 to bring maximum project cost to $10,000,000. Agreement will fund final design, Right-of-way Acquisition and drainage and flood control improvements along Sanderson Gulch, Lipan St to the South Platte River.

 

 

Location (if applicable):

 

WBE/MBE/DBE goals that were applied, if applicable (construction, design, Airport concession contracts):

 

Are WBE/MBE/DBE goals met (if applicable)?

 

Is the contract new/a renewal/extension or amendment?

 

Was this contractor selected by competitive process or sole source?

                     

For New contracts

Term of initial contract:

 

Options for Renewal:

                     How many renewals (i.e. up to 2 renewals)?

                     Term of any renewals (i.e. 1 year each):

 

Cost of initial contract term:

 

Cost of any renewals:

 

Total contract value council is approving if all renewals exercised:

 

For Amendments/Renewals Extensions:

Is this a change to cost/pricing; length of term; terms unrelated to time or price (List all that apply)?

 

If length changing

What was the length of the term of the original contract?

 

What is the length of the extension/renewal?

 

What is the revised total term of the contract?

 

If cost changing

What was the original value of the entire contract prior to this proposed change? $1,600,000

 

What is the value of the proposed change? $1,000,000

 

What is the new/revised total value including change?  $2,600,000

 

If terms changing

Describe the change and the reason for it (i.e. compliance with state law, different way of doing business etc.)